Construction draws for small Alberta builders: what slows them down and how to keep them moving
A construction draw is money your lender releases from the loan as the build reaches agreed stages, usually after an inspector or appraiser confirms the work is in place. When a draw stalls, the cause is often paperwork, such as a missing invoice, an expired insurance certificate, an unsigned statutory declaration or something unexpected on title.
General information, not legal advice. Rules change, so check the official sources linked at the bottom before you rely on any number here.
How a draw works
The usual sequence.
Every lender runs draws a little differently, and your loan agreement is the rulebook. The general shape looks like this:
- The build reaches a stage in your draw schedule, or a percentage of completion.
- You send a draw request with your supporting documents.
- The lender sends an inspector or appraiser to confirm the work in place.
- The lender reviews the package and usually checks title.
- Funds are released, less any holdback and fees.
Steps 3 and 4 are mostly out of your hands. Steps 1 and 2, and how complete your package is, are yours. That is where you can save days.
The package
What lenders commonly ask for.
This is a common list, not a legal one. Your lender's list is the one that counts, so ask for it in writing before your first draw.
| Document | Why they want it | Tip |
|---|---|---|
| Draw request and cost to complete | Shows what you are asking for and that the remaining budget still finishes the job. | Use the same budget lines every draw so they can compare. |
| Trade and supplier invoices | Backs up the costs claimed. | File each invoice the day it arrives, by job and budget line. |
| Proof of payment | Shows the money reached the trades. | Save the payment confirmation next to the invoice. |
| Statutory declaration | A sworn statement that trades and suppliers have been paid to date. | Get it signed before draw week, not during it. |
| Insurance certificate | Shows the build is insured for the period. | Check the expiry before you send. An expired one stops the file. |
| Inspection or appraisal report | Confirms the stage is complete. | Book it as soon as you know the stage date. |
| Permits and City inspection results | Shows the work passed. | Keep the latest result for each permit in one place. |
Holdback in Alberta
How the 10% holdback works.
Alberta's Prompt Payment and Construction Lien Act says an owner who is liable on a contract under which a lien may arise must, when making payment, retain 10% of the value of the work actually done and materials actually furnished. Under section 18, that holdback is kept for 60 days from the date a certificate of substantial performance is issued, or from the date the contract is completed if no certificate is issued. For contracts primarily for concrete, the period is 90 days.
If you build for a client, the same Act sets payment timing too. Section 32.2 says an owner must pay a proper invoice no later than 28 days after receiving it, and an owner who disputes it must give notice within 14 days. Section 32.1 says proper invoices must be given at least every 31 days, subject to the regulations.
For your draws, track holdback per trade, per job, from the first invoice. When it comes due, you want the number ready, not rebuilt from bank statements. This is general information, not legal advice. Read the Act and talk to your lawyer about your contracts.
What slows draws down
Seven things that stall a draw.
- An invoice missing, or sitting in someone's truck.
- An insurance certificate that expired last week.
- A statutory declaration nobody asked for until the lender did.
- Costs coded to different budget lines than last time.
- Something registered on title that you did not know about.
- The inspector or appraiser booked late.
- A package sent in pieces, so the lender reviews it three times.
The routine
Eight steps to keep draws moving.
- File as it arrives. Every invoice goes to the job and budget line the day it lands.
- Record holdback per trade as you pay each invoice.
- Track insurance expiry dates and ask your broker for the renewal certificate before it lapses.
- Collect declarations with invoices, not on draw day.
- Run your draw checklist a week out. Anything missing gets chased that day.
- Book the inspector or appraiser early once you know the stage date.
- Check title before you submit, so a surprise is yours to sort out first.
- Send one complete package. One email, everything attached, named clearly.
None of this is hard. It is just constant, and it lands at night. Site Office keeps my invoices, holdbacks and draw records as they arrive, so on draw day I am checking a list instead of digging through email. If you are working out whether to hire help or buy software for this, I compared software, a VA and a done for you back office. My pricing is public.
Questions
Short answers.
What is a construction draw?
A release of loan money as the build reaches agreed stages, usually after an inspector or appraiser confirms the work is in place.
How long does a draw take?
It depends on your lender and how complete your package is. Ask your lender for their normal turnaround and send one complete package to stay inside it.
What is the holdback in Alberta?
Under section 18 of the Prompt Payment and Construction Lien Act, an owner retains 10% of the value of work done and materials furnished for 60 days from the certificate of substantial performance or completion, or 90 days for concrete contracts. General information, not legal advice.
What is a statutory declaration in a draw?
A sworn statement, commonly asked for by lenders, that trades and suppliers have been paid to date.
What stops a draw most often?
Paperwork gaps: missing invoices, expired insurance, unsigned declarations or something on title. A checklist run a week before the draw catches most of them.
Sources
Where these facts come from.
If you want this off your plate
See it run on a real build.
I will walk you through my own build for 20 minutes, live, and tell you straight whether it fits yours. Call or text me at 780 995 7744.
Keep reading
More from the blog.
- How to book a City of Edmonton inspection and avoid reinspection fees
- How to get subcontractors to respond: a follow up schedule that works
- Certificates of insurance from subcontractors: what to collect and how to keep it current
- Edmonton home builder admin help: software, a VA, or a done for you back office?