City inspections · Edmonton
How to book a City of Edmonton inspection and avoid reinspection fees
Book a City of Edmonton building inspection from your project dashboard on selfserve.edmonton.ca, or by calling 311, once the permit is issued and the work is ready. To avoid a reinspection fee, cancel before 12 pm on the business day before if you are not ready, and make sure the address is posted, the inspector can get in safely and every old deficiency is fixed.
General information, not legal advice. Rules change, so check the official sources linked at the bottom before you rely on any number here.
Why this matters
A failed inspection costs a fee and a few days.
I build infill homes in Edmonton. Inspections are where a schedule either holds or slides. When one fails for a silly reason, you pay a fee, you lose the slot, and the trade behind it waits.
The failures that hurt most have nothing to do with workmanship. The address is not posted. The stairs have no handrail. Nobody unlocked the door. The work was booked a day early. All of that is admin, and all of it can be fixed before the inspector shows up.
This is the checklist I use. Every City rule below comes from the City pages listed at the bottom, so check them before you rely on a number.
What gets inspected
The four building inspections on a typical house.
For single family, semi detached and row housing up to four units, the City's building inspection guide lists four required building inspections, each at a different stage:
- Footing and foundation, before backfill. Footings, foundation walls, weeping tile and damp proofing.
- Framing. City stamped approved drawings must be on site, including the roof truss and floor system package. The inspector checks trusses, bearing points, bracing and blocking, and that the build matches the engineered layouts.
- Insulation and vapour barrier. Built to the Energy Code approved drawings, with a weathertight envelope and a continuous air barrier.
- Final building. Smoke and carbon monoxide alarms, handrails, guards, egress and basement insulation, plus your documentation.
Electrical, HVAC, plumbing and gas permits carry their own inspections on top of these. Put every one on the same list so nothing hides.
Step by step
How to book an inspection in Edmonton.
- Confirm the permit is issued. The City will not book an inspection on a permit that has not been issued. The guide also says work must begin within 90 days of the permit being issued, and permits expire 24 months from the date of issue. Put both dates in your calendar on day one.
- Request it in Self Serve. Open the project dashboard on selfserve.edmonton.ca and request the inspection there. If you cannot get in, call 311. From outside Edmonton the number is 780 442 5311.
- Request before 12 pm. If the City still has capacity, it is scheduled for the next business day. Once a day is full it disappears and you pick a later date. The guide says inspections are typically completed on the day requested.
- Know the method. The City uses in person inspections, Remote Video Inspections (RVI) and Verification of Compliance (VOC). Be ready for whichever one applies to your permit.
- Prepare the site the day before. Use the checklist further down.
- Read the result the same day. The outcomes are Acceptable, Acceptable with conditions, or Unacceptable. Unacceptable means a reinspection is needed before you proceed, so line up the fix and the rebooking right away.
The fee
The four reasons the City charges a reinspection fee.
The City's 2026 residential fee schedule charges a reinspection fee of $285 every time a reinspection is needed for one of the reasons below. Check the current figure on the City fee schedule before you budget, because fees are updated.
| Reason in the fee schedule | How to avoid it |
|---|---|
| No address on site | Post the municipal address where it is visible from the street, on the building or suite as applicable. The guide says the address must be visible from the street. |
| Inspector cannot get in | Unlock it, clear the path, contain pets. In an occupied home, someone 18 or older must be there to give access. |
| Not ready for inspection | Walk the stage yourself the afternoon before. If it is not ready, cancel before 12 pm the business day before instead of hoping. |
| Old deficiency not fixed | Keep the last inspection report open on your phone and tick off every item before you rebook. |
Late cancellations count too. You can cancel or reschedule in Self Serve or through 311. The cutoff to cancel without a reinspection fee is 12 pm on the business day before the inspection. Cancel later than that and reinspection fees apply.
Safe access
Unsafe access fails the inspection before it starts.
The City's June 2026 builder newsletter reminded builders that inspectors cannot enter a site with safety hazards. The examples it gave were unstable entry ramps, unprotected floor openings, and stairways with five or more risers missing proper handrails. If access is not safe, the inspection fails, which means delay and possibly a reinspection fee.
The City points builders to the Safe Access tab on its residential inspections page for examples of what is acceptable. Look at it once with your framer and your site lead. It takes ten minutes and saves a fee.
Print this
The day before checklist.
- Permit issued and the inspection shows as booked in Self Serve.
- Copies of the permits and the City approved plans on site. For framing, include the truss and floor system package.
- Address posted and visible from the street.
- Safe way in: solid ramp or steps, floor openings covered or guarded, temporary handrails on stairs.
- Site unlocked or someone there. Pets secured.
- Work at the stage being inspected is finished, not nearly finished.
- Every item from the last report fixed.
- Trades told the slot, so nobody covers up work before it is seen.
- If it is not ready, cancel before 12 pm the business day before.
Keeping track
One list for every permit and inspection.
On a two unit infill you can have a dozen inspections open across building, electrical, plumbing, gas and HVAC. Booking one is easy. Remembering which are open, which failed and what comes next is the hard part.
I keep every open permit and inspection on one list with the next step beside it. Site Office keeps that list for me now, and lines up each next step for me to say yes to. If you want help with this and are not sure what kind, I compared software, a virtual assistant and a done for you back office for Edmonton builders. My pricing is public.
Questions
Short answers.
How do I book a building inspection in Edmonton?
Request it from your project dashboard on selfserve.edmonton.ca. If you cannot use Self Serve, call 311, or 780 442 5311 from outside Edmonton. The permit must be issued first.
How soon can I get an inspection?
Request before 12 pm and, if the City has capacity left, it is scheduled for the next business day. Full days are not offered, so you pick a later date.
What is the cancellation cutoff?
12 pm on the business day before the inspection. Cancel later than that and reinspection fees apply.
How much is the reinspection fee?
The City's 2026 residential fee schedule lists $285 per reinspection. Check the current figure on the City fee schedule page, because fees change.
What documents need to be on site?
Copies of the permits and the City approved plans. For framing, the City stamped drawings including the roof truss and floor system package.
Sources
Where these facts come from.
- City of Edmonton, Building Inspection Process guide (booking, cutoffs, required inspections, outcomes)
- City of Edmonton, Planning and Development Fee Schedules, effective January 1, 2026 (reinspection fee, Appendix A)
- City of Edmonton, fee listing page (current fee schedules)
- City of Edmonton, Building Edmonton newsletter, June 2026 (safe access for inspectors)
- City of Edmonton, Residential inspections page (Safe Access tab)
If you want this off your plate
See it run on a real build.
I will walk you through my own build for 20 minutes, live, and tell you straight whether it fits yours. Call or text me at 780 995 7744.
Keep reading
More from the blog.
- How to get subcontractors to respond: a follow up schedule that works
- Construction draws for small Alberta builders: what slows them down and how to keep them moving
- Certificates of insurance from subcontractors: what to collect and how to keep it current
- Edmonton home builder admin help: software, a VA, or a done for you back office?